FDOT Road Construction Update

Florida Department of Transportation, Image of traffic signals and FDOT logo.

Image of SR 858/Hallandale Beach Boulevard Street View.

SR 858/Hallandale Beach Boulevard Safety Improvements Project

Start Date: July 29, 2019

Completion Date: Spring 2020

Financial Number: 436111-1-52-01

Project Length: .17 miles

Project Limits: SR 858/Hallandale Beach Boulevard from east of the South Florida Rail Corridor (SFRC) crossing to the west of Ansin Boulevard

Contractor: Weekley Asphalt Paving, Inc

Estimated Construction Cost: $2,257,890

Scope of Work:

Project improvements include milling and resurfacing the existing pavement along Hallandale Beach Boulevard from the SFRC crossing to west of Ansin Boulevard; widening and resurfacing the I-95 northbound off-ramp to Hallandale Beach Boulevard, to provide an additional right-turn lane; widening and resurfacing the I-95 southbound off-ramp to Hallandale Beach Boulevard, to extend vehicle storage capacity of the right-turn lane; upgrading the existing traffic signals at the intersections of Hallandale Beach Boulevard and the I-95 off-ramps; reconstructing the sidewalks and pedestrian crossings on the I-95 northbound off-ramp to Hallandale Beach Boulevard; and upgrading the existing lighting along the I-95 off-ramps to Hallandale Beach Boulevard and underneath the I-95 bridge to LED lighting.


Meeting Invitation and Project Flyer - Hallandale Beach Blvd Safety Improvements

Image SR 824/Pembroke Road at Dixie Highway Intersection Street View.

SR 824/Pembroke Road at Dixie Highway Intersection Improvements Project

Start Date: August 28, 2019

Completion Date: Spring 2020

Financial Number: 430590-2-52-01

Project Length: .05 miles

Project Limits: SR 824/Pembroke Road from west of Dixie Highway to east of South 21st Avenue/Northeast 1st Avenue

Contractor: Florida Safety Contractors, Inc.

Estimated Construction Cost: $815,678

Scope of Work:

Project improvements include upgrading signalized intersections to mast arms; installing crosswalks, pedestrian signal crossings, and associated curb ramps; upgrading existing lighting to LED; and milling and resurfacing the roadway.


Project Flyer - Pembroke Road at Dixie Improvements

Image of SR 9/I-95 at SR 824/Pembroke Road Interchange Street View.

SR 9/I-95 at SR 824/Pembroke Road Interchange Improvements Project

Start Date: September 25, 2019

Completion Date: Spring 2020

Financial Number: 436303-1-52-02

Project Length: 1 mile

Project Limits: SR 9/I-95 on and off-ramps at the SR 824/Pembroke Road Interchange

Contractor: Halley Engineering, Inc.

Estimated Construction Cost: $1,465,257

Scope of Work:

Project improvements include widening the I-95 off-ramps at Pembroke Road to accommodate an additional right turn lane; minor shoulder widening of the I-95 on-ramps at Pembroke Road; upgrading the existing traffic signals at the intersections of Pembroke Road and the I-95 off-ramps; upgrading the existing lighting along the I-95 on and off-ramps at Pembroke Road to LED lighting; reconstructing the sidewalks and pedestrian crossings at the I-95 off-ramps and the I-95 northbound on-ramp at Pembroke Road; and milling and resurfacing within the project limits.


Meeting Invitation and Project Flyer - I-95 at Pembroke Road Interchange

Image of 14th Avenue Mobility Improvements Project,- Street View.

14th Avenue Mobility Improvements Project

Start Date: December 2, 2019

Completion Date: Spring 2021

Financial Number: 434690-1-52-01

Project Length: 2.7 miles

Project Limits: 14th Avenue from Atlantic Shores Boulevard to Sheridan Street

Contractor: Acosta Tractors, Inc.

Estimated Construction Cost: $2,099,354

Scope of Work:

Project improvements include widening the roadway to accommodate bike lanes on 14th Avenue, Arthur Street, and Harding Street; adding shared lane pavement markings along 14th Avenue and Harding Street, to enhance the safe travel of bicycles and motor vehicles in the same traffic lane; and installing a shared-use path (off-road path) on Polk Street and 14th Avenue.

Meeting Invitation and Flyer - 14 Avenue Mobility Improvements Project




Facebook Twitter Email

Other News in Main News Flash (Home Page)

Extended Hours

Extended Hours

Posted on: October 12, 2019
Utility Bill Increase

Water and Sewer rates will Increase

Posted on: October 5, 2019
5 years Capital Improvement Projects , Picture of the Skyline

Capital Improvement Plan

Posted on: September 19, 2019
Bus Shelter

FDOT Bus Shelter Improvements Project

Posted on: September 19, 2019